Isle of Man Steam Packet Terminal - Liverpool

The current and future terminals. This gallery has been created as it appears surveying work has begun around the Waterloo River Entrance site (June 2017) which has been suggested as a replacement terminal.

Images are posted in reverse chronological order. The most recent photographs appear first.
Read More
  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Progress on the Terminal Building as of May 05, 2022.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Red 7 Marine jack up HAVEN SEARISER working on a berthing dolphin.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Red 7 Marine jack up HAVEN SEARISER working on a berthing dolphin.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Red 7 Marine jack up HAVEN SEARISER working on a berthing dolphin.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Progress on the Terminal Building as of May 05, 2022.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Red 7 Marine jack up HAVEN SEARISER working on a berthing dolphin.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Progress on the Terminal Building as of May 05, 2022.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Progress on the Terminal Building as of May 05, 2022.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Progress on the Terminal Building as of May 05, 2022.

  • Terminal construction progress as of May 05, 2022

    Terminal construction progress as of May 05, 2022

    Progress on the Terminal Building as of May 05, 2022.

  • Terminal construction progress as of March 28, 2022

    Terminal construction progress as of March 28, 2022

    Work appears to be getting underway at the south end of the building to apply the cladding.

  • Terminal construction progress as of March 28, 2022

    Terminal construction progress as of March 28, 2022

    Work appears to be getting underway at the south end of the building to apply the cladding.

  • Terminal construction progress as of March 28, 2022

    Terminal construction progress as of March 28, 2022

    Work appears to be getting underway at the south end of the building to apply the cladding.

  • Terminal construction progress as of March 28, 2022

    Terminal construction progress as of March 28, 2022

    Red 7 Marine jack up HAVEN SEARISER

  • Terminal construction progress as of March 28, 2022

    Terminal construction progress as of March 28, 2022

    Red 7 Marine jack up HAVEN SEARISER

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    General view of the site from the river.

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    Red 7 Marine Jack Up Platform HAVEN SEARISER.

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    General view of the site from the river.

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    The first of the berthing dolphins in place.

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    The first of the berthing dolphins in place.

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    Red 7 Marine jack up HAVEN SEARISER

  • Terminal construction progress as of March 25, 2022

    Terminal construction progress as of March 25, 2022

    Red 7 Marine jack up HAVEN SEARISER

  • Terminal construction progress as of March 24, 2022

    Terminal construction progress as of March 24, 2022

    Carmet Towing Company's CT OXTON seen with the jackup platform.

  • Terminal construction progress as of March 17, 2022

    Terminal construction progress as of March 17, 2022

    The McGregor built linkspan for the new terminal which is currently sored on the river wall opposite Trafalgar Dock. This appears to be a floating linkspan. The pontoon is the separate section to the right